The Journal · July 11, 2026 · 8 min read · By Émilie, Head of Content

How long does renovating an apartment take?

Right after budget, this is the question every client asks. The honest answer: between the first meeting and the handover of keys, allow 6 to 12 months for a full renovation in Paris. Here is the breakdown, phase by phase — and what really moves the schedule.

The two main phases — and why the first matters so much.

A renovation is not only weeks on site. It starts with an invisible preparation phase that shapes everything else:

The rule ten years of projects have taught us: a well-prepared project is a site without surprises. Rushing the design to "start sooner" is the surest way to blow the schedule.

How long by scope.

The timeline depends first on how deep the intervention goes. Our real-world ranges in Paris:

Type of projectDesignWorksIndicative total
Refresh (paint, floors, one bathroom)2 – 4 wks3 – 6 wks~ 2 months
Full renovation (services redone, kitchen, bathrooms, finishes)2 – 3 months4 – 6 months6 – 9 months
Heavy / high-end renovation (new layout, structure, custom millwork)3 months6 – 10 months9 – 12 months and up

A useful benchmark: on a Paris apartment, allow on average one to two weeks of works per 10 m² for a full renovation — more as soon as structure is involved or exceptional finishes are the goal.

The typical schedule of a 90 m², week by week.

To give these ranges a concrete shape, here is the typical sequence of a full 90 m² apartment renovation — the order of magnitude of our La Main d'Or project, delivered in 3 months. Every site has its own particulars: this schedule is a reference point, not a promise.

WeeksPhaseWhat happens
1 – 2Set-up & demolitionProtecting common areas, strip-out, removing partitions and fittings, clearing rubble
3 – 4ServicesSetting out new partitions, running plumbing, electrics and ventilation
5 – 6PlasteringLinings, suspended ceilings, closing partitions after the services have been checked
7 – 8Substrates & wet roomsScreeds and levelling, waterproofing, tiling of bathrooms
9 – 10SurfacesParquet and flooring, internal joinery, preparing surfaces for paint
11 – 12Technical finishesPaint, kitchen installation, sanitaryware, electrical fittings, lighting
13HandoverMillwork, touch-ups, end-of-site cleaning, pre-handover inspection and snagging

To which you must add, upstream, the 2 to 3 months of design — and the anticipation of lead times: the kitchen installed in week 11 was ordered during the design phase, not during the works.

What stretches a project.

Two apartments of the same size can have very different schedules. The real drivers:

The real enemy of the schedule is not the site — it is indecision. A kitchen chosen in week 2 is built during the works, with no impact. The same kitchen chosen in week 20 pushes back the whole end of the project. Over the length of a renovation, the client's decisions weigh as much as the trades' work.

Renovating while living on site — or not?

The question comes up on almost every project. Our position is clear: on a full renovation, living in the middle of the works is a false economy.

Staying on site does make sense for a room-by-room refresh with no work on the services. In every other case, the cost of a temporary rental is generally lower than what occupation loses you in weeks on site — and in peace of mind.

Our real timelines.

Rather than a theoretical average, here is what we actually deliver:

The range is wide because ambition is: it is precisely the job of a proper study to give you, from the outset, a credible handover date.

How to hold the schedule.

A schedule that is met is not luck, it is method. Ours, as a general contractor:

A project of this kind? Tell us about it in a few lines: we come back to you within 48 hours with a first reading — scope, order of magnitude, realistic timeline.

Five questions to check a schedule is realistic.

Before committing to a date, ask these five questions — the answers speak volumes:

Three frequent questions.

Can a Paris apartment be fully renovated in 2 months?

For a refresh, yes: that is precisely the order of magnitude of this format (2 to 4 weeks of preparation, 3 to 6 weeks of works). For a full renovation with services redone, no — compressing below 3 months of works is paid for in the finishes. Our low-end reference remains 90 m² in 3 months, with complete preparation upstream.

What is the best time of year to start?

The moment your design is finished. A well-prepared site launched in November progresses better than a poorly prepared one launched in April. The only real Paris constraint: factoring suppliers' August closures into the procurement calendar.

What happens if the site runs late?

It all depends on your contract. In the classic setup, delay is negotiated company by company. With a general contractor, the handover date is a contractual commitment carried by a single responsible party — one of the key points in the choice between the two setups.

Every project has its own rhythm: tell us about yours, and we will come back to you within 48 hours with a first estimate — timeline included.

★★★★★5.012 GOOGLE REVIEWS

"Many thanks to Anthony and his team for their professionalism, their advice and the quality of the work. The result is refined and exactly what I expected." (translated)Adrien A. · Google review

Read the reviews →

A project, a delivery date?

Get an estimate

← All articles

Just a question? Write to us — answer within 48 h, no commitment.

Write to usEstimate