The Journal · August 21, 2026 · 7 min read · By Émilie, Head of Content
Prior declaration, planning permit, heritage architect opinion, general meeting consent: in Paris, paperwork usually decides the start date. Here is how to frame it from day one.
Almost everything follows from that distinction. Works that stay strictly internal — new floors, paint, a kitchen, a bathroom, renewed electrics and plumbing — require no planning formality at all, provided they create no floor area, do not alter the external appearance of the building and do not change the property's designated use category. That covers the majority of the apartment renovations we run.
As soon as the project crosses the façade — a window replaced with a different model, a new opening, a balustrade, a roof light, air conditioning fixed outside — it falls within the scope of a prior declaration. And as soon as it creates floor area, or touches the structure in the context of a change of designated use, it moves up to a planning permit. Be careful not to merge the two registers: planning and co-ownership are two separate authorisations, and a purely internal project may owe nothing to the town hall while still requiring a vote at a general meeting.
| Nature of the works | Planning formality | Review (complete file) |
|---|---|---|
| Internal renovation with no new floor area and no façade change | None | — |
| Change to the external appearance (windows, new opening, façade or roof elements) | Prior declaration | 1 month (2 with heritage review) |
| Creation of 5 to 20 m² of floor area (up to 40 m² in urban zones covered by a local plan) | Prior declaration | 1 month (2 with heritage review) |
| Floor area beyond those thresholds, extension, roof raising | Planning permit | 2 months (single-family house) or 3 months |
| Change of designated use with structural or façade modification | Planning permit | 3 months |
| Change of designated use without touching structure or façade | Prior declaration | 1 month (2 with heritage review) |
Two useful clarifications. First, appointing an architect becomes mandatory once total floor area exceeds 150 m² after the works — a threshold quickly reached on an extension or a roof raising. Second, these periods only start once a complete file has been lodged: a request for additional documents issued by the case officer within the first month restarts the clock when those documents arrive. A carefully assembled file is not administrative politeness, it is site time earned.
A large part of the Paris fabric sits within the setting of a listed monument or inside a designated heritage area. In those perimeters the file goes to the Architecte des Bâtiments de France, the state heritage architect, whose opinion conditions the authorisation and extends the review by one month. In practice, a simple prior declaration to replace windows moves from one month to two — and the opinion may prescribe precise characteristics: material, profile, colour, glazing divisions, balustrade type.
Good practice is to settle this before locking in the choices, not after a refusal. On period buildings, where the façade and joinery are part of the property's value, the constraint usually aligns with the interest of the project: it is the logic we apply on heritage properties, set out on our hôtel particulier renovation page.
It is the leading cause of delay we see on Paris renovations — well ahead of the town hall. Three situations call for a general meeting resolution:
The critical point is not the vote itself, it is the meeting calendar. One ordinary general meeting a year means a project arriving in May may wait until the following spring, unless an extraordinary meeting is called — and paid for. That constraint belongs in the conversation at the offer stage, not at the quotation stage. Add to it reading the co-ownership rules, notifying the managing agent, providing insurance certificates, agreeing access and protection of common parts, and observing the working hours set by local order in Paris.
The habit that saves months: handle permissions during the design phase, not after it. The 2 to 3 months of design on a full renovation are exactly the time needed to assemble a file, obtain a heritage opinion and clear a general meeting. Run in parallel, those periods vanish from the programme; run in series, they are added to it.
The two notions are often conflated, yet they answer to different authorities and different files. Change of destination is a planning matter: it describes moving from one category to another — offices converted into a home, for instance — and calls for a prior declaration, or a planning permit where the load-bearing structure or the façade is modified. Change of use is a separate regime, particularly strict in Paris: turning residential premises into something else requires the City's authorisation, sometimes with a compensation obligation.
The direction of travel therefore matters as much as the nature of the change: converting offices into housing restores homes, whereas the reverse removes them from the stock. Our Trocadéro project illustrates the first case — a former law firm of 227 m² in the 16th arrondissement returned to residential use, with sixteen coordinated trades over ten months. On the commercial side, premises receiving the public add their own authorisation, with a safety commission review depending on the category: we cover that in our guide to office renovation in Paris.
An authorisation obtained is not immediately secure. Three sequences follow one another, and only the last one allows a comfortable start:
In a co-owned building, add the wait until the next general meeting. That is why a Paris project subject to a permit is planned several months before the first skip arrives — a framing we detail in our article on how long a Paris renovation really takes.
In the classic set-up, the client sits alone between their architect, their managing agent and the case officer. As a general contractor, these steps are part of our scope: we identify the applicable formality at the first visit, assemble the file, engage with the heritage architect where consulted, prepare the resolution put to the general meeting, and build those periods into the contractual programme — exactly as we do for the coordination of all the trades.
One note of caution: this guide gives bearings, not legal advice. The applicable rule depends on the local plan, the exact heritage perimeter and the configuration of the property. Verification is done case by case — it is the first thing we do on any apartment renovation in Paris.
If the works stay internal, do not alter the external appearance, create no floor area and do not change the designated use category, no planning formality is required. Co-ownership consent is still needed as soon as the works touch common parts — load-bearing walls, risers, service ducts — or the external appearance of the building.
A prior declaration covers works altering the external appearance without creating significant floor area, and the creation of 5 to 20 m² of floor area — raised to 40 m² in urban zones covered by a local plan. Beyond that, or when a change of designated use also modifies the load-bearing structure or the façade, a planning permit is required. An architect becomes mandatory once total floor area exceeds 150 m² after the works.
Allow one month of review for a prior declaration, two months for a permit on a single-family house and three months in other cases — each extended by one month where the heritage architect is consulted, which is common in Paris. Add the two-month third-party appeal window from the on-site notice, and the wait for the next general meeting in a co-owned building.
The best time to deal with paperwork is before it becomes a problem: describe your project and we will tell you within 48 hours which formalities apply and what they mean for the schedule.
"Many thanks to Anthony and his team for their professionalism, their advice and the quality of the work. The result is refined and exactly what I expected." (translated)Adrien A. · Google review
Read the reviews →Just a question? Write to us — answer within 48 h, no commitment.